Midway through a product release cycle, a senior vice president instructs two Developers to move an executive dashboard to the top of the Product Backlog ahead of regulatory compliance work. Under the 2020 Scrum Guide, what is the governing rule for Product Backlog ordering?
The Product Owner is solely accountable for Product Backlog ordering, so executives must convince the Product Owner.
A governance committee of executives and Developers votes weekly to reprioritize urgent Product Backlog items.
The Scrum Master directly reorders the Product Backlog whenever leadership flags a higher-visibility priority.
Developers may place urgent executive items at the top of the Product Backlog provided they inform the Product Owner.
Show the answer
A. The Product Owner is solely accountable for Product Backlog ordering, so executives must convince the Product Owner.
According to the 2020 Scrum Guide, the Product Owner is one person—not a committee—who is solely accountable for maximizing product value and effective Product Backlog management, including ordering items. While the Product Owner may delegate tasks to others, they remain accountable, and anyone wishing to change the Product Backlog must do so by trying to convince the Product Owner.
Halfway through a two-week Sprint, the Developers discover that a payment-gateway integration is far more complex than expected and that two lower-priority Sprint Backlog items cannot be finished, although the Sprint Goal remains achievable. According to the 2020 Scrum Guide, what should occur?
The Scrum Master extends the Sprint timebox by four days so the team finishes every item forecasted in Sprint Planning.
The Developers temporarily relax automated regression tests so every originally selected Sprint Backlog item is completed.
The Developers renegotiate Sprint Backlog scope with the Product Owner while keeping the Sprint Goal and quality intact.
The Scrum Team immediately cancels the Sprint because any scope change invalidates the initial Sprint Backlog forecast.
Show the answer
C. The Developers renegotiate Sprint Backlog scope with the Product Owner while keeping the Sprint Goal and quality intact.
The 2020 Scrum Guide states that the Sprint Goal is the single objective and commitment for the Sprint Backlog, creating coherence and focus while allowing flexibility regarding the exact work needed to achieve it. During the Sprint, quality does not decrease, the Sprint timebox is fixed, and scope may be clarified and renegotiated with the Product Owner as more is learned without endangering the Sprint Goal.
Reference: The 2020 Scrum Guide — The Sprint & Sprint Backlog Commitment (Sprint Goal)
At the end of a Sprint, a Product Backlog item satisfies all feature-specific acceptance criteria written by the Product Owner, but automated security scans required by the Scrum Team's Definition of Done (DoD) have not been completed. Under the 2020 Scrum Guide, how must this item be handled?
It is demonstrated as a completed Increment at the Sprint Review and marked partially done for conditional approval.
It cannot be released or presented at the Sprint Review and must return to the Product Backlog for later consideration.
The Product Owner may waive the security scan requirement because feature acceptance criteria supersede the DoD.
The Developers carry the item into a dedicated hardening Sprint to finish security testing outside the Product Backlog.
Show the answer
B. It cannot be released or presented at the Sprint Review and must return to the Product Backlog for later consideration.
Per the 2020 Scrum Guide, the Definition of Done is the formal description of the state of the Increment when it meets the quality measures required for the product (distinct from item-specific acceptance criteria). If a Product Backlog item does not meet the Definition of Done, it cannot be released or even presented at the Sprint Review; instead, it returns to the Product Backlog for future consideration.
Reference: The 2020 Scrum Guide — Increment Commitment: Definition of Done