Mixed practice drill

10 realistic exam questions, graded as you go, with the exact rule or statute citation for every answer. Start free, no sign-up.

Timed mock exam

40 questions in 48 minutes, drawn from every topic. No answers shown until the end, then a full score breakdown, your weakest topics and a review of what you missed.

Practise by topic

Sample questions

Midway through a product release cycle, a senior vice president instructs two Developers to move an executive dashboard to the top of the Product Backlog ahead of regulatory compliance work. Under the 2020 Scrum Guide, what is the governing rule for Product Backlog ordering?

  1. The Product Owner is solely accountable for Product Backlog ordering, so executives must convince the Product Owner.
  2. A governance committee of executives and Developers votes weekly to reprioritize urgent Product Backlog items.
  3. The Scrum Master directly reorders the Product Backlog whenever leadership flags a higher-visibility priority.
  4. Developers may place urgent executive items at the top of the Product Backlog provided they inform the Product Owner.
Show the answer

A. The Product Owner is solely accountable for Product Backlog ordering, so executives must convince the Product Owner.

According to the 2020 Scrum Guide, the Product Owner is one person—not a committee—who is solely accountable for maximizing product value and effective Product Backlog management, including ordering items. While the Product Owner may delegate tasks to others, they remain accountable, and anyone wishing to change the Product Backlog must do so by trying to convince the Product Owner.

Reference: The 2020 Scrum Guide — Scrum Team: Product Owner Accountability

A manufacturing automation project has a Budget at Completion (BAC) of $600,000 over a 12-month baseline. At the end of Month 6, the team planned to complete 50% of the scope (PV = $300,000), has actually earned 40% of the total scope, and has recorded $280,000 in Actual Cost (AC). What are the Cost Variance (CV) and Schedule Variance (SV), and what is the project status?

  1. CV is +$40,000 and SV is +$60,000, confirming the project is operating under budget and ahead of schedule.
  2. CV is -$40,000 and SV is -$60,000, confirming the project is operating over budget and behind schedule.
  3. CV is -$20,000 and SV is -$60,000, indicating spending exceeds planned value while progress lags the baseline.
  4. CV is -$60,000 and SV is -$40,000, meaning cost performance is worse than schedule performance.
Show the answer

B. CV is -$40,000 and SV is -$60,000, confirming the project is operating over budget and behind schedule.

Earned Value (EV) equals 40% of the $600,000 BAC, or $240,000. Per the PMI PMBOK Guide Earned Value Management formulas, CV = EV - AC = $240,000 - $280,000 = -$40,000 (over budget) and SV = EV - PV = $240,000 - $300,000 = -$60,000 (behind schedule). Both negative variances confirm unfavorable cost and schedule performance.

Reference: PMI PMBOK Guide (7th Ed.) & Process Groups: A Practice Guide — Earned Value Analysis

Halfway through a two-week Sprint, the Developers discover that a payment-gateway integration is far more complex than expected and that two lower-priority Sprint Backlog items cannot be finished, although the Sprint Goal remains achievable. According to the 2020 Scrum Guide, what should occur?

  1. The Scrum Master extends the Sprint timebox by four days so the team finishes every item forecasted in Sprint Planning.
  2. The Developers temporarily relax automated regression tests so every originally selected Sprint Backlog item is completed.
  3. The Developers renegotiate Sprint Backlog scope with the Product Owner while keeping the Sprint Goal and quality intact.
  4. The Scrum Team immediately cancels the Sprint because any scope change invalidates the initial Sprint Backlog forecast.
Show the answer

C. The Developers renegotiate Sprint Backlog scope with the Product Owner while keeping the Sprint Goal and quality intact.

The 2020 Scrum Guide states that the Sprint Goal is the single objective and commitment for the Sprint Backlog, creating coherence and focus while allowing flexibility regarding the exact work needed to achieve it. During the Sprint, quality does not decrease, the Sprint timebox is fixed, and scope may be clarified and renegotiated with the Product Owner as more is learned without endangering the Sprint Goal.

Reference: The 2020 Scrum Guide — The Sprint & Sprint Backlog Commitment (Sprint Goal)

A data-center migration project has a Budget at Completion (BAC) of $500,000. At a milestone review, Earned Value (EV) is $200,000, Planned Value (PV) is $250,000, and Actual Cost (AC) is $250,000. Management expects the current cost-efficiency rate to persist for all remaining work. What is the Estimate at Completion (EAC)?

  1. $550,000, calculated by adding the remaining uncompleted work at the original budgeted rate onto actual costs.
  2. $400,000, calculated by multiplying the $500,000 BAC by the cumulative CPI of 0.80.
  3. $625,000, calculated by dividing the $500,000 BAC by the cumulative CPI of 0.80.
  4. $718,750, calculated by dividing the remaining work by the product of CPI and SPI before adding actual costs.
Show the answer

C. $625,000, calculated by dividing the $500,000 BAC by the cumulative CPI of 0.80.

First compute CPI = EV / AC = $200,000 / $250,000 = 0.80. When current cost performance is expected to continue for the rest of the project (typical variance), the PMBOK Guide formula is EAC = BAC / CPI = $500,000 / 0.80 = $625,000. Using AC + (BAC - EV) = $550,000 applies only when past variances are atypical one-time anomalies.

Reference: PMI PMBOK Guide & Process Groups: A Practice Guide — Control Costs (EAC Forecasting)

At the end of a Sprint, a Product Backlog item satisfies all feature-specific acceptance criteria written by the Product Owner, but automated security scans required by the Scrum Team's Definition of Done (DoD) have not been completed. Under the 2020 Scrum Guide, how must this item be handled?

  1. It is demonstrated as a completed Increment at the Sprint Review and marked partially done for conditional approval.
  2. It cannot be released or presented at the Sprint Review and must return to the Product Backlog for later consideration.
  3. The Product Owner may waive the security scan requirement because feature acceptance criteria supersede the DoD.
  4. The Developers carry the item into a dedicated hardening Sprint to finish security testing outside the Product Backlog.
Show the answer

B. It cannot be released or presented at the Sprint Review and must return to the Product Backlog for later consideration.

Per the 2020 Scrum Guide, the Definition of Done is the formal description of the state of the Increment when it meets the quality measures required for the product (distinct from item-specific acceptance criteria). If a Product Backlog item does not meet the Definition of Done, it cannot be released or even presented at the Sprint Review; instead, it returns to the Product Backlog for future consideration.

Reference: The 2020 Scrum Guide — Increment Commitment: Definition of Done

Exams this helps with

ExamAgency / IssuerRegion
Scrum.org PSM I & PSPO I AssessmentScrum.orgGlobal / Online
PMI Project Management Professional (PMP) ExamProject Management InstituteGlobal / Online
PMI Certified Associate in Project Management (CAPM)Project Management InstituteGlobal / Online
ASQ Certified Six Sigma Green Belt (CSSGB)ASQGlobal / Online
ITIL 4 Foundation Certification ExamPeopleCert / AXELOSGlobal / Online