PMP, CAPM, Scrum, Six Sigma & ITIL 4: practice drill
10 realistic exam questions, graded as you go, with the exact rule or statute citation for every answer. Start free, no sign-up.
Timed mock exam
26 questions in 31 minutes, drawn from every topic. No answers shown until the end, then a full score breakdown, your weakest topics and a review of what you missed.
Prices are in US dollars, plus tax where it applies. Stripe, our payment processor, calculates tax at checkout.
All sales are final. If something is really wrong, such as a duplicate charge or a purchase that does not unlock what you bought, write to support@careerexampro.com and we will put it right.
One-time payment. Nothing renews.
You have an exam ticket for this practice test. Start the timed mock exam to use it.
Exact question counts, passing scores, and allowed reference materials vary by testing window and state/agency. Always confirm current rules with the official testing provider.
Sample questions
Midway through a product release cycle, a senior vice president instructs two Developers to move an executive dashboard to the top of the Product Backlog ahead of regulatory compliance work. Under the 2020 Scrum Guide, what is the governing rule for Product Backlog ordering?
The Product Owner is solely accountable for Product Backlog ordering, so executives must convince the Product Owner.
A governance committee of executives and Developers votes weekly to reprioritize urgent Product Backlog items.
The Scrum Master directly reorders the Product Backlog whenever leadership flags a higher-visibility priority.
Developers may place urgent executive items at the top of the Product Backlog provided they inform the Product Owner.
Show the answer
A. The Product Owner is solely accountable for Product Backlog ordering, so executives must convince the Product Owner.
According to the 2020 Scrum Guide, the Product Owner is one person—not a committee—who is solely accountable for maximizing product value and effective Product Backlog management, including ordering items. While the Product Owner may delegate tasks to others, they remain accountable, and anyone wishing to change the Product Backlog must do so by trying to convince the Product Owner.
A manufacturing automation project has a Budget at Completion (BAC) of $600,000 over a 12-month baseline. At the end of Month 6, the team planned to complete 50% of the scope (PV = $300,000), has actually earned 40% of the total scope, and has recorded $280,000 in Actual Cost (AC). What are the Cost Variance (CV) and Schedule Variance (SV), and what is the project status?
CV is +$40,000 and SV is +$60,000, confirming the project is operating under budget and ahead of schedule.
CV is -$40,000 and SV is -$60,000, confirming the project is operating over budget and behind schedule.
CV is -$20,000 and SV is -$60,000, indicating spending exceeds planned value while progress lags the baseline.
CV is -$60,000 and SV is -$40,000, meaning cost performance is worse than schedule performance.
Show the answer
B. CV is -$40,000 and SV is -$60,000, confirming the project is operating over budget and behind schedule.
Earned Value (EV) equals 40% of the $600,000 BAC, or $240,000. Per the PMI PMBOK Guide Earned Value Management formulas, CV = EV - AC = $240,000 - $280,000 = -$40,000 (over budget) and SV = EV - PV = $240,000 - $300,000 = -$60,000 (behind schedule). Both negative variances confirm unfavorable cost and schedule performance.
Reference: PMI PMBOK Guide (7th Ed.) & Process Groups: A Practice Guide — Earned Value Analysis
Halfway through a two-week Sprint, the Developers discover that a payment-gateway integration is far more complex than expected and that two lower-priority Sprint Backlog items cannot be finished, although the Sprint Goal remains achievable. According to the 2020 Scrum Guide, what should occur?
The Scrum Master extends the Sprint timebox by four days so the team finishes every item forecasted in Sprint Planning.
The Developers temporarily relax automated regression tests so every originally selected Sprint Backlog item is completed.
The Developers renegotiate Sprint Backlog scope with the Product Owner while keeping the Sprint Goal and quality intact.
The Scrum Team immediately cancels the Sprint because any scope change invalidates the initial Sprint Backlog forecast.
Show the answer
C. The Developers renegotiate Sprint Backlog scope with the Product Owner while keeping the Sprint Goal and quality intact.
The 2020 Scrum Guide states that the Sprint Goal is the single objective and commitment for the Sprint Backlog, creating coherence and focus while allowing flexibility regarding the exact work needed to achieve it. During the Sprint, quality does not decrease, the Sprint timebox is fixed, and scope may be clarified and renegotiated with the Product Owner as more is learned without endangering the Sprint Goal.
Reference: The 2020 Scrum Guide — The Sprint & Sprint Backlog Commitment (Sprint Goal)