PMP Predictive, EVM Math & Risk Management practice drill
10 realistic exam questions, graded as you go, with the exact rule or statute citation for every answer. Start free, no sign-up.
Sample questions
A manufacturing automation project has a Budget at Completion (BAC) of $600,000 over a 12-month baseline. At the end of Month 6, the team planned to complete 50% of the scope (PV = $300,000), has actually earned 40% of the total scope, and has recorded $280,000 in Actual Cost (AC). What are the Cost Variance (CV) and Schedule Variance (SV), and what is the project status?
CV is +$40,000 and SV is +$60,000, confirming the project is operating under budget and ahead of schedule.
CV is -$40,000 and SV is -$60,000, confirming the project is operating over budget and behind schedule.
CV is -$20,000 and SV is -$60,000, indicating spending exceeds planned value while progress lags the baseline.
CV is -$60,000 and SV is -$40,000, meaning cost performance is worse than schedule performance.
Show the answer
B. CV is -$40,000 and SV is -$60,000, confirming the project is operating over budget and behind schedule.
Earned Value (EV) equals 40% of the $600,000 BAC, or $240,000. Per the PMI PMBOK Guide Earned Value Management formulas, CV = EV - AC = $240,000 - $280,000 = -$40,000 (over budget) and SV = EV - PV = $240,000 - $300,000 = -$60,000 (behind schedule). Both negative variances confirm unfavorable cost and schedule performance.
Reference: PMI PMBOK Guide (7th Ed.) & Process Groups: A Practice Guide — Earned Value Analysis
A data-center migration project has a Budget at Completion (BAC) of $500,000. At a milestone review, Earned Value (EV) is $200,000, Planned Value (PV) is $250,000, and Actual Cost (AC) is $250,000. Management expects the current cost-efficiency rate to persist for all remaining work. What is the Estimate at Completion (EAC)?
$550,000, calculated by adding the remaining uncompleted work at the original budgeted rate onto actual costs.
$400,000, calculated by multiplying the $500,000 BAC by the cumulative CPI of 0.80.
$625,000, calculated by dividing the $500,000 BAC by the cumulative CPI of 0.80.
$718,750, calculated by dividing the remaining work by the product of CPI and SPI before adding actual costs.
Show the answer
C. $625,000, calculated by dividing the $500,000 BAC by the cumulative CPI of 0.80.
First compute CPI = EV / AC = $200,000 / $250,000 = 0.80. When current cost performance is expected to continue for the rest of the project (typical variance), the PMBOK Guide formula is EAC = BAC / CPI = $500,000 / 0.80 = $625,000. Using AC + (BAC - EV) = $550,000 applies only when past variances are atypical one-time anomalies.
Reference: PMI PMBOK Guide & Process Groups: A Practice Guide — Control Costs (EAC Forecasting)
During a monthly steering committee review, a project manager presents Earned Value metrics showing a Schedule Performance Index (SPI) of 1.15 and a Cost Performance Index (CPI) of 0.82. Which assessment accurately describes the project's status?
The project is ahead of schedule because SPI exceeds 1.00, but over budget because CPI is below 1.00.
The project is behind schedule and under budget because CPI is below 1.00 while SPI exceeds 1.00.
The project is ahead of schedule and under budget because earned value outpaces planned value and actual cost.
The project is behind schedule and over budget because an SPI above 1.00 signals elapsed duration overruns.
Show the answer
A. The project is ahead of schedule because SPI exceeds 1.00, but over budget because CPI is below 1.00.
In PMI Earned Value Management, index values greater than 1.00 are favorable and values below 1.00 are unfavorable. An SPI of 1.15 (EV / PV > 1) means the project has completed 15% more value than planned (ahead of schedule), whereas a CPI of 0.82 (EV / AC < 1) means it earns only $0.82 per dollar spent (over budget)—a common result of overtime or crashing.